PROJECTS / KG3-042 · TOWER B / OVERVIEW
PROJECT 042 · LOS ANGELES, CA

Tower B — Civic Square

Phase
Structural · L3
Owner
Civic Square LLC
Schedule
2025-09-01 → 2027-04-30
Progress
38% · ON TRACK
RFIs Open
12
+3 this week
Photos · Apr
1,840
+218 vs last mo.
Daily Logs
47/47
100% submitted
Hours On Site
9,142
+412 this week

Open RFIs & field changes

12 OPEN · 4 IN REVIEW
IDTitleTradeFiledStatus
RFI-0118Rebar spacing at column C-7Concrete04-25 · 14:30Open
RFI-0117HVAC rough-in clash · L4 corridorMEP04-24 · 16:08In Review
RFI-0116Door swing conflict · stair BArchitectural04-24 · 11:42Open
RFI-0115Slab thickness deviation L3Structural04-23 · 09:14Escalated
RFI-0114Conduit run · electrical roomMEP04-22 · 15:30In Review
RFI-0113Curtain wall mullion alignmentArchitectural04-22 · 08:55Resolved

Today

APR 25
14:30
RFI-0118 filed by J. Ortega
Voice note · 1:24 · 3 photos
11:42
Concrete pour completed · L3
12 cu. yd. · Inspector signed off
10:08
Inspector arrived
Pre-pour walkthrough · L3
09:14
Steel delivery · bay 3
4 photos · GPS tagged
07:42
Crew check-in
14 workers · 4 trades
07:00
Site open
Foreman J. Ortega